08 Apr 2013 16:40 #1 by Iaurkano
holidays management was created by Iaurkano
hi babynus,

how can i manage ressource holidays,

using the calendar i can set days off for everybody, but for each ressource who is in holidays during a specific week(s), how can i manage this.

thank's in advance.

Best regards.

Please Log in or Create an account to join the conversation.

More
08 Apr 2013 19:48 #2 by babynus
Replied by babynus on topic Re: holidays management
Use Administrative Projets.

For instance, create an administrative project "Off days", with tasks "Holidays", "Sickness", "Training".
Then resources enter real work on these activitities (no need to assign of affect resources to administrative projects)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
09 Apr 2013 08:33 #3 by Iaurkano
Replied by Iaurkano on topic Re: holidays management
Ok,

thank's a lot.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.