I have 4 projects in my Projeqtor. The first is a simple test and has the number 1 id.
My principal project has the id #2 and all the WBS begins with 2.
I deleted the first project. But the WBS still begins with 2 for my principal project.
No, never update direcly the database.
You may get unexpected result.
To force recalculation of WBS, just reorder the level.
To do this, in the planning view, create new projet "Draft".
It will get WBS 3.
Then drag&drop Draft to move it on first place.
It will get WBS 1.
Move "Draft" back to last position.
You main project will get WBS 1.
You can now deleted project "Draft"
It seems long, but it's easier to do than to descripbe what to do
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.