When I run the report for project expense per month (costs -> project expense per month), the planned work (planned project expense) is never calculated although I've entered planned amount for a project expense. - The yellow field within this report is always empty.
The real work is correctly calculated on the real amount of the entered project expense.
Unfortunatly I can not attach a screenshot to this post
The planned value is not displayed when a real value exists for the expense !
This is to be able to get a sum that will reflect reality as near as possible : real expense when exists, planned when not exists, and avoid counting twice an expense (as planned and as real).
Every report dealing with planned and reals works this way.
For instance the "work planned" and "detailed monthly plannig" reports work this way.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.