Hi,
First, don't use Tickets, but Activities.
Then you must define one Activity for each item, and you may regroupe them :
- under a structure top Activity or top Project
- on a dedicated Activity type.
for instance :
=> create activities types (if not already existing)
.1) Spec
.2) Dev
.3) Integ
.4) Func
=> Create 2 resources :
.1) A
.2) B
=> Create activities this way :
.1) "F1", type Func
..2) "Spec1", type Spec, parent F1, Assigned to A
..3) "Dev1", type Dev, parent F1, Assigned to B
..4) "Integ1", type Integ, parent F1, Assigned to A
.5) "F2", type Func
..6) "Spec2", type Spec, parent F2, Assigned to A
..7) "Dev2", type Dev, parent F2, Assigned to B
..8 ) "Integ2", type Integ, parent F2, Assigned to A
For each activity, either define a duration and select planning mode = "Fixed duration" or enter assigned work for each resource on each assigned activity.
Go to Planning view and draw dependencies as you described them.
Run planning.
You won !!!!