07 Sep 2013 00:43 #1 by brightonbob
Hi babynus

First thanks for creating this great tool. Looks like a lot of intelligent work has gone into this product!

I am still learning Project'Or RIA; creating dummy projects, reading manual and browsing forums etc. I am struggling a little with some of the terminology and discovering the best/recommend workflow to setup and manage a "standard" project.

Is there a (video) tutorial or similar?

Q1) I work on international projects, many have standard working weeks Sunday - Thursday. How can I best change the default calendar settings i.e. To Fri/Sat non working or remove?

Q2) My projects have many repeating tasks (e.g. weekly program meeting every Thursday for 3hrs at 3PM, Onsite backup tape change etc). What is the best way to schedule ongoing, repeating tasks like these?

Q3) Is there a way to change the size of the top, horizontal menu items? (I can see how to change the left, main menu icon sizes).

Q4) Is there a way to edit the items on the main, left menu (delete, hide, reorder etc)?

Q5) What is the best way to add a field e.g. Add Skype ID to a Contact?

Thanks in advance for any help on these.

BB

Please Log in or Create an account to join the conversation.

More
07 Sep 2013 11:43 #2 by babynus
Replied by babynus on topic New user questions

Is there a (video) tutorial or similar?

No.
It is planned to provide some video tutorials, but this service will not be free ...

Q1) I work on international projects, many have standard working weeks Sunday - Thursday. How can I best change the default calendar settings i.e. To Fri/Sat non working or remove?

On the calendar, click all fridays (they will become closed days) and click and click all sunday (they will become open days). But keep in mind that this will be applied to all projects and resources : today, there is one only calendar. An evolution is planned to provided sevaral calendars and affect resources to one of these (Ticket #714).

Q2) My projects have many repeating tasks (e.g. weekly program meeting every Thursday for 3hrs at 3PM, Onsite backup tape change etc). What is the best way to schedule ongoing, repeating tasks like these?

Periodic meetings !!!

Q3) Is there a way to change the size of the top, horizontal menu items? (I can see how to change the left, main menu icon sizes).

No

Q4) Is there a way to edit the items on the main, left menu (delete, hide, reorder etc)?

Hide : remove rights on the screen "access to forms".
Reorder : change order in table menu (pay attention to preserve hierarchic position (idMenu = id of top menu)

Q5) What is the best way to add a field e.g. Add Skype ID to a Contact?

Add field in the database (table contact), add definition in the class script (/model/Contact.php). That's all :woohoo:

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.