23 Oct 2018 16:03 #1 by apad
Rate allocation was created by apad
Hi

I'm playing with Rate Allocation on projects and Rate assignment on activities.
I'm wondering if Rate is only an information about availability or if Rate is used by planning calculation ?
If Rate is used by calculation, can you explain how ?

Regards

Please Log in or Create an account to join the conversation.

More
23 Oct 2018 16:23 #2 by Gautier
Replied by Gautier on topic Rate allocation
Hello,

Yes, rate is used by planning calculation.
You should read "Allocations section" and "Assignment section" in our user guide, press F1.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.