I have a problem when I reopen an activity or a project: the handled, done and closed dates disappear .
For the closed date I can understand, but why the other two dates also disappear?
I'm forced to memorise them to retype when I reopen the objet.
Is it the normal behaviour?
I tried it in a version 6.3.5 but also in démo version (7.3.1).
It all depends on configuration of status "reopened"
On default configuration, "reopened" is a status that is "not in progress" and "not done".
So handled (in progress) and done are unchecked and dates are cleared.
To preserve handled and done dates, just check correspondong macro status on status "reopened"
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.