30 Nov 2021 14:16 #1 by GROUDILLON
When we set a mandatory checklist on activities, we can't mark the activitie as "Done" if checklist is not fullfilled. => that's ok

But, if we have an activities, with Result field not empty, when we set the remaining time to "0" on the timesheet, its status change to "Done" even if checklist is not satisfied.
Of course, the activity type require checklist to be fulfilled
 

Please Log in or Create an account to join the conversation.

More
30 Nov 2021 15:38 #2 by babynus
Replied by babynus on topic issue with checklist
Hi

It seems that mandatory checklist is not controlled when status is moved from Timesheet
Ticket #5854 recorded

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.