Reports:
How can i find the number of hours assigned daily to a resource in order to know whether his 8 hours are already booked or some are still free (to be able to complete it).
Hi, thank you for your response.
If I'm right, in this report i see the available hours only when the resource has recorded his time in the "Real work allocation" form.
What i want to see exactly is the total amount of time left or assigned to a resource after creating a task and assigning an amount of time to it (before the resource complete the "Real work allocation" form).
No, the report pointed out by climb4fun is the one you're looking for.
If some work is planned for a resource, availability takes it into account.
For information, when availability is reduced only because of planned work, available work is displayed in italic.
When availability is reduced because of real work, available work is displayed straight.
Below the step followed:
1. Create a new task (T1) – in the « Progress » section added 3 hours as duration and validated it for 2012/02/08
2. Saved the task (T1) with status=recorded
3. Assigned a resource (R1) to the task with 3 hours also assigned to him (in the « Assignment » section)
4. Saved the task (T1) as with status=assigned
In the « Real work allocation » for resource R1, the assigned 3 hours are visible in the columns « assigned » and « planned » which is correct – but in this page the daily allocated time are not visible
In the « Monthly availability of resources » report (Follow-up -> Reports -> planning -> monthly availability of resources), for resource R1 the number of available hours is still 8 not 5 as expected.
In the « Real work allocation » for resource R1, the assigned 3 hours are visible in the columns « assigned » and « planned » which is correct – but in this page the daily allocated time are not visible
Yes it is ! If you check "Show planned work" (on top right) you should see planned work in small blue characters.
In the « Monthly availability of resources » report (Follow-up -> Reports -> planning -> monthly availability of resources), for resource R1 the number of available hours is still 8 not 5 as expected.
It should.
Did I miss something?
YES !
In fact, work in not already planned : you must go to the planning screen and run planning (calculation is not automatic)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.