ProjeQtOr free project management software - Activity fixed duration : can't change avancement planning view - ProjeQtOr
 
 

Activity fixed duration : can't change avancement planning view

More
06 Feb 2024 15:56 - 15 Apr 2024 14:12 #1 by jmmbb
Hello,

with an activity set "fixed duration", charge set and no assignation, i can't change avacement value in planning view.
It work fine in activity view.
Let show screen capture :
From planning, avancement is locked
 
From activity, it's fine :
 

Regards,
Attachments:
Last edit: 15 Apr 2024 14:12 by jmmbb.

Please Log in or Create an account to join the conversation.

More
07 Feb 2024 09:29 #2 by Arkhanje
Hello,

indeed, I reproduce and it is not normal
Ticket #8019  recorded

Please Log in or Create an account to join the conversation.

More
07 Feb 2024 14:17 #3 by jmmbb
The same way, being able to modify the avancement value directly in the right part of gantt (like description,...) will be usefull :
 
Attachments:

Please Log in or Create an account to join the conversation.

More
08 Feb 2024 10:12 #4 by Arkhanje
good idea ! I add it to the ticket!

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.061 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.