Hi,
Really, I cannot reproduce your issue.
I've tried several databases and all is ok for me : project leader can access to Gantt planning.
I also tried to reproduce your case :
- started from empty database
- connect with admin
- create 1 user : projectleader, profile Project Leader, also a resource called "Project Leader"
- updated data access so that projectleader can create project : defined right as creator+ to Project screen for profile Project Leader
- updated data access so that projectleader can create affectations to projects he is not affected to (to be able to self affect) : define right as manager+ to Affectation screen for profile Project Leader
- disconnect
- connect as projectleader
- create 8 projects Project1 to Project8
- affect Project Leader to the 8 projects
- disconnect and reconnect projectleader to retrieve correct acces rights to the new projects
- see gannt chant : 8 projects are displayed
- create 2 tickets (ticket1 and ticket2) and 3 milestones : milestone1 to milestone3 on project project1
- see gannt chant : 8 projects and 3 milestones are displayed
All is OK for me.
I uploaded some databases exports so that you can test :
-
projectorria.toolware.fr/files/projectorria_v17.sql
: some existing default data I use to generate manual screenshots
-
projectorria.toolware.fr/files/projectorria_test.sql
: result of upper tests
Maybe you can try and import it to test :
- use phpmyadmin
- create emty database
- import file into this new database
- change pamareters.php file to point out to this database
If you still reproduce the issue on your database, please profide as much data as possible :
- print screen for gantt view, affectations, users, activities
- maybe, if your database does not include confidential data, you can send an export of the databse
Send this to
This email address is being protected from spambots. You need JavaScript enabled to view it.
Thanks.