07 Jan 2021 18:47 #1 by SL
Hello,

Maybe it is already treated in another forum but I did not find it.
Sometimes workload activity permits to finish tasks before the planned date. Therefore, I cannot close the task and I received the message "Unable to close an element with left work"
For example, I finished a task using 77% of the planned workload. What is the best way to during the validation process permitting to increase the progress status from 77% up to 100%?

Best regards

Please Log in or Create an account to join the conversation.

More
08 Jan 2021 20:26 #2 by babynus
Just set the left work to zero.
It can be done on timesheet or on the activity.

You can also set specific access rigfht "can force close" to true.
This will automatically set left work to zero when closing.
But in my opinion setting left work to zero when closing the activity is too late.
You should set it to zero as soon as activity is done.
 

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: SL

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.