[SOLVED] Import of activities for a project

More
21 Mar 2018 16:18 #1 by FF
Hi folks,

I have just started using projeqtor and I really like the concept.
Actually I am trying to import the activities from a csv through "Tools - Import data", that represent a project that already has started in November 2017.

All tasks turn out to be listed under each other at today's date with the duration of 1 and a progress of 0.

Those fields seem automatically to be set to a default although I filled in the
planned duration with a number of days (automatically set to 1)
progress with 0 or 20 or 100 (automatically set to 0)
planned start & end date with the dates of the tasks (automatically set to today's date)

I also have exported a Example-task and reimported it (with a different task name). It does not show the same like the original.

What am I doing wrong?

Cheers, FF

ProjeQtOr V7.0.0
Attachments:

Please Log in or Create an account to join the conversation.

More
22 Mar 2018 00:14 #2 by babynus
Planned data are never imported : they are calculated from other data : work and constraints.

You miss one point : assignments.
You need to assign work to a resource for a given activity to have real capacity planning calculation.

Other way to do, if you just need the drawing of a planning, is to use "fixed duration" planning mode for activities.
Then you'll have to specify validated duration.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
22 Mar 2018 11:30 - 22 Mar 2018 11:40 #3 by FF
Thanks for your reply.

For the future tasks we cannot assign resources as the contractors are not decided yet. I might set up a dummy contractor for this - perhaps it works out.

If not, where do I set up the tasks as "fixed duration"? I just had a look into the General Settings and did not find it.
Is it a Project's attribute?


ProjeQtOr V7.0.0
Attachments:
Last edit: 22 Mar 2018 11:40 by FF.

Please Log in or Create an account to join the conversation.

More
22 Mar 2018 12:02 #4 by FF
Ok, found it and set all tasks to "feste Dauer" i.e. "fixed duration and imported again.

The task turned out at today's date with duration 1 instead of 2.






ProjeQtOr V7.0.0
Attachments:

Please Log in or Create an account to join the conversation.

More
22 Mar 2018 13:11 #5 by FF
Before we solve that, I will enter all the tasks by hand. No problem.

I did another test and entered tree tasks belonging to a phase and having confirmed start and end dates (in the past).
In the status "recorded" they show up fine in the planning.
When I change a task from "recorded" to "assigned" the Planned Dates are set to today and the Planned Duration is set to 1.
That occurs independently with tasks set to "ASAP" or "Fixed Duration".

How do I manage to enter tasks properly?

Goal is:
1. Set up the Project Plan like it was planned.
2. Save a baseline.
3. Modify the tasks that already have been assigned to persons and either are "Done" or being worked on.
4. Then the succeeding tasks should delay according to the delays the project actually has. The project's end is expected to delay as well.
5. Saving an additional baseline of today.
6. In the future all Users whom tasks are assigned to should put in the days of work they have spent and the percentage of progress and the Planning is expected to adapt.

Is there a tutorial for the program?

Sorry for bothering you.
FF

ProjeQtOr V7.0.0

Please Log in or Create an account to join the conversation.

More
22 Mar 2018 16:29 #6 by babynus
"Fixed duration" is a planning mode, defined on activities

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.074 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.