09 Oct 2019 13:45 #1 by LEADER
Hello,

I have an issue since last update for project status. When i create a meeting and close it, the status of the project is modified with meeting status.

For example, Project Alpha, status is: In progress
I create a live meeting (affected to project Alpha), realize the meeting and close the meeting --> status = Close
The status of the project alpha is modified to closed.


Plugin version of Livemeeting = 1.4
Projeqtor version: 8.2.2

Please Log in or Create an account to join the conversation.

More
10 Oct 2019 11:17 #2 by Gautier
Hello,

No worry ,this is not an issue and it is not your plugin. It is your configuration.
You have to check in your global parameters -> activity -> automation -> auto set parent activity status -> yes.

When you activate this parameter :
If you have only one activity ( or meeting ect ..) to your project, with this parameter your project status will change according to your activity.
If you have many activities your project status will change when all activities will have the same status if the workflow allow it.
The following user(s) said Thank You: LEADER

Please Log in or Create an account to join the conversation.

More
11 Oct 2019 14:04 #3 by LEADER
Hello

Thank you a lot, it is OK now

Regards